How are differences between actual costs and allowances settled?

Prepare for the AIA Contract Document A201 with engaging flashcards and multiple-choice questions. Understand contract fundamentals and get ready to excel in your exam with detailed hints and explanations.

Multiple Choice

How are differences between actual costs and allowances settled?

Explanation:
When a contract uses allowances, any gap between the actual costs and the budgeted allowance is settled by Change Orders. Allowances cover items not fully defined; once the work is actually priced, the contract sum is adjusted to reflect the real cost through a Change Order. If the actual cost is less than the allowance, the unused portion is credited to the owner; if it’s more, the owner pays the difference via the Change Order. This mechanism keeps the pricing transparent and signed off by both parties, rather than leaving differences unresolved or handled separately.

When a contract uses allowances, any gap between the actual costs and the budgeted allowance is settled by Change Orders. Allowances cover items not fully defined; once the work is actually priced, the contract sum is adjusted to reflect the real cost through a Change Order. If the actual cost is less than the allowance, the unused portion is credited to the owner; if it’s more, the owner pays the difference via the Change Order. This mechanism keeps the pricing transparent and signed off by both parties, rather than leaving differences unresolved or handled separately.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy