If nonconforming work is discovered, what may the Architect require?

Prepare for the AIA Contract Document A201 with engaging flashcards and multiple-choice questions. Understand contract fundamentals and get ready to excel in your exam with detailed hints and explanations.

Multiple Choice

If nonconforming work is discovered, what may the Architect require?

Explanation:
When nonconforming work is found, the Architect has the authority to require that the work be corrected, which can involve removal and replacement or modification so that it conforms to the contract documents. Any additional costs needed to bring the work into conformance are added to the contract sum, reflecting the extra work and keeping the project aligned with the agreed documents. This ensures defective work is addressed through proper process and cost adjustment, rather than requiring a full repricing of the contract, allowing the Owner to replace work unilaterally, or letting a Subcontractor accept nonconforming work to avoid delays.

When nonconforming work is found, the Architect has the authority to require that the work be corrected, which can involve removal and replacement or modification so that it conforms to the contract documents. Any additional costs needed to bring the work into conformance are added to the contract sum, reflecting the extra work and keeping the project aligned with the agreed documents. This ensures defective work is addressed through proper process and cost adjustment, rather than requiring a full repricing of the contract, allowing the Owner to replace work unilaterally, or letting a Subcontractor accept nonconforming work to avoid delays.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy