If the contractor receives an approved submittal, is he relieved of responsibility for deviations from the contract documents?

Prepare for the AIA Contract Document A201 with engaging flashcards and multiple-choice questions. Understand contract fundamentals and get ready to excel in your exam with detailed hints and explanations.

Multiple Choice

If the contractor receives an approved submittal, is he relieved of responsibility for deviations from the contract documents?

Explanation:
Approved submittals confirm that proposed products, systems, or workmanship align with the design intent, but they do not remove the contractor’s obligation to comply with the contract documents. The contractor remains responsible for ensuring that the work, including its means and methods, meets all contract requirements. If a deviation is needed or discovered, it must be addressed through the contract modification process (such as a change order) to update the contract documents, rather than being exempted simply because a submittal was approved. So, no—the contractor is not relieved of responsibility for deviations just because a submittal was approved.

Approved submittals confirm that proposed products, systems, or workmanship align with the design intent, but they do not remove the contractor’s obligation to comply with the contract documents. The contractor remains responsible for ensuring that the work, including its means and methods, meets all contract requirements. If a deviation is needed or discovered, it must be addressed through the contract modification process (such as a change order) to update the contract documents, rather than being exempted simply because a submittal was approved. So, no—the contractor is not relieved of responsibility for deviations just because a submittal was approved.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy