Instructions given to the superintendent are binding as if given to whom?

Prepare for the AIA Contract Document A201 with engaging flashcards and multiple-choice questions. Understand contract fundamentals and get ready to excel in your exam with detailed hints and explanations.

Multiple Choice

Instructions given to the superintendent are binding as if given to whom?

Explanation:
The superintendent is the contractor’s agent on the job site, so instructions given to the superintendent are binding as if they were given to the contractor itself. This means the contractor is responsible for carrying out or enforcing those directions, since the superintendent directly oversees construction activities, means and methods, and daily coordination. The owner or architect may issue guidance or clarifications, but the binding directives on how the work is performed come through the contractor via the superintendent. Subcontractors receive direction from the contractor, not directly from the owner or architect.

The superintendent is the contractor’s agent on the job site, so instructions given to the superintendent are binding as if they were given to the contractor itself. This means the contractor is responsible for carrying out or enforcing those directions, since the superintendent directly oversees construction activities, means and methods, and daily coordination. The owner or architect may issue guidance or clarifications, but the binding directives on how the work is performed come through the contractor via the superintendent. Subcontractors receive direction from the contractor, not directly from the owner or architect.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy