What can be assumed about submittals delivered by the contractor to the architect?

Prepare for the AIA Contract Document A201 with engaging flashcards and multiple-choice questions. Understand contract fundamentals and get ready to excel in your exam with detailed hints and explanations.

Multiple Choice

What can be assumed about submittals delivered by the contractor to the architect?

Explanation:
Submittals are a tool for coordination and verification. The contractor is responsible for reviewing each submittal and ensuring it aligns with the contract documents, including checking field measurements and coordinating with other work before sending it to the architect for review. The architect’s role is to review for conformance with the design intent, not to relieve the contractor of responsibility for deviations. Therefore, the best answer says the submittals have been reviewed and approved by the contractor and that materials have been verified against field measurements and coordination. This captures that the submittal image or data represents the contractor’s due-diligence in measurement and coordination, before the architect reviews for compatibility with the design. The other options imply automatic architect approval, no further review, or relieving the contractor of responsibility, which do not reflect how submittals function in practice.

Submittals are a tool for coordination and verification. The contractor is responsible for reviewing each submittal and ensuring it aligns with the contract documents, including checking field measurements and coordinating with other work before sending it to the architect for review. The architect’s role is to review for conformance with the design intent, not to relieve the contractor of responsibility for deviations. Therefore, the best answer says the submittals have been reviewed and approved by the contractor and that materials have been verified against field measurements and coordination. This captures that the submittal image or data represents the contractor’s due-diligence in measurement and coordination, before the architect reviews for compatibility with the design. The other options imply automatic architect approval, no further review, or relieving the contractor of responsibility, which do not reflect how submittals function in practice.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy