What does the amount of the change order reflect?

Prepare for the AIA Contract Document A201 with engaging flashcards and multiple-choice questions. Understand contract fundamentals and get ready to excel in your exam with detailed hints and explanations.

Multiple Choice

What does the amount of the change order reflect?

Explanation:
Change orders are used to adjust the contract sum when the scope of work changes. The amount shown on a change order represents the net cost impact of that change: it includes the difference between what the work will actually cost and what was assumed in the contract’s allowances, plus any changes in the contractor’s costs caused by the change (such as labor, materials, equipment, subcontractors, and related overhead). This captures the full financial effect of the change, not just a single component. It isn’t limited to the architect’s fees and overhead, nor is it simply the owner’s contingency or only subcontractor costs.

Change orders are used to adjust the contract sum when the scope of work changes. The amount shown on a change order represents the net cost impact of that change: it includes the difference between what the work will actually cost and what was assumed in the contract’s allowances, plus any changes in the contractor’s costs caused by the change (such as labor, materials, equipment, subcontractors, and related overhead). This captures the full financial effect of the change, not just a single component. It isn’t limited to the architect’s fees and overhead, nor is it simply the owner’s contingency or only subcontractor costs.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy