What happens when the Owner and Contractor cannot agree on a proposed change in A201?

Prepare for the AIA Contract Document A201 with engaging flashcards and multiple-choice questions. Understand contract fundamentals and get ready to excel in your exam with detailed hints and explanations.

Multiple Choice

What happens when the Owner and Contractor cannot agree on a proposed change in A201?

Explanation:
When the Owner and Contractor can’t agree on a proposed change, the Architect issues a Construction Change Directive to authorize the change temporarily while the final Change Order is negotiated. This keeps the work moving and provides a defined scope, timing, and cost framework for the change in the interim. The contractor proceeds as directed, and the final amounts and adjustments are resolved later through a Change Order. This is not a unilateral change by the contractor, and it isn’t a Stop Work Order; those are different tools with separate purposes. The CCD specifically serves as a temporary authorization to proceed so the project isn’t delayed while terms are hammered out.

When the Owner and Contractor can’t agree on a proposed change, the Architect issues a Construction Change Directive to authorize the change temporarily while the final Change Order is negotiated. This keeps the work moving and provides a defined scope, timing, and cost framework for the change in the interim. The contractor proceeds as directed, and the final amounts and adjustments are resolved later through a Change Order. This is not a unilateral change by the contractor, and it isn’t a Stop Work Order; those are different tools with separate purposes. The CCD specifically serves as a temporary authorization to proceed so the project isn’t delayed while terms are hammered out.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy