What is a Schedule of Values (SOV) and how is it used in progress payments under A201?

Prepare for the AIA Contract Document A201 with engaging flashcards and multiple-choice questions. Understand contract fundamentals and get ready to excel in your exam with detailed hints and explanations.

Multiple Choice

What is a Schedule of Values (SOV) and how is it used in progress payments under A201?

Explanation:
The Schedule of Values is an itemized breakdown of the total contract price by specific work activities. It provides the basis for progress payments by tying the amount paid to the value of work actually performed on each item. As portions of the work are completed (or partially completed), the corresponding line items in the SOV become earned value, which the architect can certify for payment, typically with retainage applied. The SOV is updated to reflect changes or modifications to the contract, so payments stay aligned with current progress. It’s not a payroll list of subcontractors, not a tax accounting document, and not just a calendar of milestones used only for reporting.

The Schedule of Values is an itemized breakdown of the total contract price by specific work activities. It provides the basis for progress payments by tying the amount paid to the value of work actually performed on each item. As portions of the work are completed (or partially completed), the corresponding line items in the SOV become earned value, which the architect can certify for payment, typically with retainage applied. The SOV is updated to reflect changes or modifications to the contract, so payments stay aligned with current progress. It’s not a payroll list of subcontractors, not a tax accounting document, and not just a calendar of milestones used only for reporting.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy