What is the typical function of a Construction Change Directive in the change process?

Prepare for the AIA Contract Document A201 with engaging flashcards and multiple-choice questions. Understand contract fundamentals and get ready to excel in your exam with detailed hints and explanations.

Multiple Choice

What is the typical function of a Construction Change Directive in the change process?

Explanation:
A Construction Change Directive is the tool used to authorize a change in the work immediately, even when the exact price and schedule impact haven’t been agreed yet. It directs the contractor to proceed with the change, so the project isn’t delayed waiting for formal negotiations. The financial and time implications are resolved afterward through Change Orders that document the agreed adjustments. This arrangement helps keep the project moving when a modification is necessary but the parties haven’t settled the final numbers. It’s not about prohibiting changes, nor about finalizing costs instantly, and it can affect scope, time, and price—not just the schedule.

A Construction Change Directive is the tool used to authorize a change in the work immediately, even when the exact price and schedule impact haven’t been agreed yet. It directs the contractor to proceed with the change, so the project isn’t delayed waiting for formal negotiations. The financial and time implications are resolved afterward through Change Orders that document the agreed adjustments.

This arrangement helps keep the project moving when a modification is necessary but the parties haven’t settled the final numbers. It’s not about prohibiting changes, nor about finalizing costs instantly, and it can affect scope, time, and price—not just the schedule.