What mechanism authorizes changes in the work before price/time is agreed?

Prepare for the AIA Contract Document A201 with engaging flashcards and multiple-choice questions. Understand contract fundamentals and get ready to excel in your exam with detailed hints and explanations.

Multiple Choice

What mechanism authorizes changes in the work before price/time is agreed?

Explanation:
Construction Change Directive is the mechanism that authorizes a change in the work before the price or time is agreed. In AIA A201, when a modification is needed but the cost and schedule haven’t been settled yet, the Architect issues a Construction Change Directive directing the contractor to proceed with the change. This keeps the project moving while negotiations catch up, and the final price and schedule are later formalized in a Change Order once terms are agreed. Substantial Completion is simply a milestone, not a method to authorize changes, and a Change Order is used after price/time have been agreed.

Construction Change Directive is the mechanism that authorizes a change in the work before the price or time is agreed. In AIA A201, when a modification is needed but the cost and schedule haven’t been settled yet, the Architect issues a Construction Change Directive directing the contractor to proceed with the change. This keeps the project moving while negotiations catch up, and the final price and schedule are later formalized in a Change Order once terms are agreed. Substantial Completion is simply a milestone, not a method to authorize changes, and a Change Order is used after price/time have been agreed.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy