What must the contractor do with re-submissions of submittals when changes have been made from the original?

Prepare for the AIA Contract Document A201 with engaging flashcards and multiple-choice questions. Understand contract fundamentals and get ready to excel in your exam with detailed hints and explanations.

Multiple Choice

What must the contractor do with re-submissions of submittals when changes have been made from the original?

Explanation:
When a submittal is resubmitted after changes, the contractor must clearly identify what was changed since the previous submission. This directs the reviewer’s attention to the updated parts—so the architect or engineer can quickly verify that the changes comply with the contract documents and avoid re-review of unchanged information. Clear indication of revisions keeps a traceable record and speeds up the approval process, especially for details like dimensions, materials, or installation methods. Why the other approaches don’t fit: submittals aren’t approved automatically as if nothing changed; changes require fresh review. Submitting a revision without noting what changed obscures modifications, causing confusion and delays. Discarding previous submittals ignores the history and rationale behind the changes, which is essential for proper coordination.

When a submittal is resubmitted after changes, the contractor must clearly identify what was changed since the previous submission. This directs the reviewer’s attention to the updated parts—so the architect or engineer can quickly verify that the changes comply with the contract documents and avoid re-review of unchanged information. Clear indication of revisions keeps a traceable record and speeds up the approval process, especially for details like dimensions, materials, or installation methods.

Why the other approaches don’t fit: submittals aren’t approved automatically as if nothing changed; changes require fresh review. Submitting a revision without noting what changed obscures modifications, causing confusion and delays. Discarding previous submittals ignores the history and rationale behind the changes, which is essential for proper coordination.