What should the architect do with submittals not required by the contract documents?

Prepare for the AIA Contract Document A201 with engaging flashcards and multiple-choice questions. Understand contract fundamentals and get ready to excel in your exam with detailed hints and explanations.

Multiple Choice

What should the architect do with submittals not required by the contract documents?

Explanation:
Submittal review is limited to what the contract documents require. If the contractor sends a submittal that isn’t called for by those documents, the architect has no obligation to review or approve it. The correct action is to return the item to the contractor without action, signaling that it lies outside the review scope. This keeps the contract responsibilities clear and avoids implying approval of items not included in the agreement. Submitting to the contractor for approval or forwarding to the owner would create or bypass a review process that isn’t defined by the contract.

Submittal review is limited to what the contract documents require. If the contractor sends a submittal that isn’t called for by those documents, the architect has no obligation to review or approve it. The correct action is to return the item to the contractor without action, signaling that it lies outside the review scope. This keeps the contract responsibilities clear and avoids implying approval of items not included in the agreement. Submitting to the contractor for approval or forwarding to the owner would create or bypass a review process that isn’t defined by the contract.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy