Who administers the contract?

Explanation:
In AIA A201, the Architect acts as the Contract Administrator, appointed to oversee and administer the contract on behalf of the Owner. This role includes handling the day-to-day administration, interpretations of the contract, processing requests for payment, and deciding on claims within the Architect’s authority. The Contractor performs the work, and the Owner funds and oversees, but the administration of the contract itself rests with the Architect. Administration continues through the progression of the project until the Final Certificate for Payment is issued; once that final certificate is issued, the contract administration duties are considered complete and the project is closed.

In AIA A201, the Architect acts as the Contract Administrator, appointed to oversee and administer the contract on behalf of the Owner. This role includes handling the day-to-day administration, interpretations of the contract, processing requests for payment, and deciding on claims within the Architect’s authority. The Contractor performs the work, and the Owner funds and oversees, but the administration of the contract itself rests with the Architect.

Administration continues through the progression of the project until the Final Certificate for Payment is issued; once that final certificate is issued, the contract administration duties are considered complete and the project is closed.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy