Who certifies the amount due for a payment application?

Prepare for the AIA Contract Document A201 with engaging flashcards and multiple-choice questions. Understand contract fundamentals and get ready to excel in your exam with detailed hints and explanations.

Multiple Choice

Who certifies the amount due for a payment application?

Explanation:
The amount due on a payment application is certified by the Architect. In AIA A201, the Contractor submits a payment request, and the Architect reviews the work completed, compares it to the contract documents and the Schedule of Values (and any approved changes), and then issues a Certificate for Payment for the amount the Owner owes for that period (including any retainage). The Owner pays the certified amount to the Contractor. This arrangement uses the Architect as an impartial verifier to ensure payment aligns with work completed and approved, rather than leaving the decision to the Contractor or Owner alone. Subcontractors don’t certify the payment amount; they’re paid through the Contractor.

The amount due on a payment application is certified by the Architect. In AIA A201, the Contractor submits a payment request, and the Architect reviews the work completed, compares it to the contract documents and the Schedule of Values (and any approved changes), and then issues a Certificate for Payment for the amount the Owner owes for that period (including any retainage). The Owner pays the certified amount to the Contractor. This arrangement uses the Architect as an impartial verifier to ensure payment aligns with work completed and approved, rather than leaving the decision to the Contractor or Owner alone. Subcontractors don’t certify the payment amount; they’re paid through the Contractor.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy