Who is responsible for notifying the architect and owner about which subcontractors will work with the contractor, and when should this occur?

Explanation:
The contractor bears the responsibility for identifying and notifying the architect and owner about which subcontractors will work on the project, and this should happen as soon as practicable after contract award. This early disclosure lets the owner and architect review the proposed subcontractors for qualifications, ensure there’s suitable coverage for each trade, and address any potential conflicts or substitutions before work ramps up. It keeps the team aligned and supports orderly coordination and procurement planning. The owner or architect don’t initiate this notification, and the subcontractor isn’t the one responsible for conveying the list.

The contractor bears the responsibility for identifying and notifying the architect and owner about which subcontractors will work on the project, and this should happen as soon as practicable after contract award. This early disclosure lets the owner and architect review the proposed subcontractors for qualifications, ensure there’s suitable coverage for each trade, and address any potential conflicts or substitutions before work ramps up. It keeps the team aligned and supports orderly coordination and procurement planning. The owner or architect don’t initiate this notification, and the subcontractor isn’t the one responsible for conveying the list.