Who must determine by inspection the date of substantial and final completion?

Prepare for the AIA Contract Document A201 with engaging flashcards and multiple-choice questions. Understand contract fundamentals and get ready to excel in your exam with detailed hints and explanations.

Multiple Choice

Who must determine by inspection the date of substantial and final completion?

Explanation:
The architect. Under the AIA A201 framework, it’s the architect who, by inspection, determines when the work has reached substantial completion and when it has reached final completion, issuing the corresponding certificates. Substantial completion means the project is sufficiently complete for its intended use, even if minor items remain on a punch list. Final completion means all contract requirements are satisfied and the work is fully complete, as certified by the architect. The owner, contractor, or a third‑party inspector do not have the authority to make these determinations under the contract.

The architect. Under the AIA A201 framework, it’s the architect who, by inspection, determines when the work has reached substantial completion and when it has reached final completion, issuing the corresponding certificates. Substantial completion means the project is sufficiently complete for its intended use, even if minor items remain on a punch list. Final completion means all contract requirements are satisfied and the work is fully complete, as certified by the architect. The owner, contractor, or a third‑party inspector do not have the authority to make these determinations under the contract.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy