Who pays the certified amount?

Prepare for the AIA Contract Document A201 with engaging flashcards and multiple-choice questions. Understand contract fundamentals and get ready to excel in your exam with detailed hints and explanations.

Multiple Choice

Who pays the certified amount?

Explanation:
The payment flow in AIA A201 is that the Owner pays the Contractor the amount the Architect certifies as due. The Architect acts as the Owner’s certifying agent: after the Contractor submits an application for payment, the Architect reviews the work, may approve or adjust, and issues a certificate for payment for the amount due. That certified amount is what the Contractor earns for that period, and the Owner then pays it, in accordance with the contract’s terms (including any retainage). The Architect certifies, but does not pay. Subcontractors are paid by the Contractor, not directly by the Owner, and the Owner does not pay the Contractor on behalf of the Architect.

The payment flow in AIA A201 is that the Owner pays the Contractor the amount the Architect certifies as due. The Architect acts as the Owner’s certifying agent: after the Contractor submits an application for payment, the Architect reviews the work, may approve or adjust, and issues a certificate for payment for the amount due. That certified amount is what the Contractor earns for that period, and the Owner then pays it, in accordance with the contract’s terms (including any retainage). The Architect certifies, but does not pay. Subcontractors are paid by the Contractor, not directly by the Owner, and the Owner does not pay the Contractor on behalf of the Architect.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy