If the contractor carries out his due diligence as set forth in sections 3.2.2 and 3.2.3 is he liable to the owner or architect for damages resulting from errors, inconsistencies, or omissions in the contract documents, differences between field measurements and the contract documents, or for nonconformity of the contract documents to applicable laws, statutes, ordinances, codes, rules and regulations, and lawful orders of public authorities?

?

No, if the contractor believes that additional cost or time has been involved because of clarifications or instructions from the architect the contractor may make claims as provided in article 15.